Friday, June 24, 2016

Kiess Drive Completed. Depot Street Work Continues

Work Completed Last week, June 20th to June 24th  
·         Kiess Drive
o   Milled existing pavement surface layer
o   Installed new asphalt pavement surface layer
·         Depot Street (South of Prairie Street), Phase I
o   Asphalt patching around new concrete curb & gutter
o   Open parking stalls for resident and commuter parking.
·         Depot Street (North of Prairie Street), Phase II
o   Closed commuter parking stalls within Phase II work area
o   Removed and replaced existing concrete curb & gutter

Work anticipated to be completed Next week, June 27th to July 1st
·         Kiess Drive
o   No significant work anticipated.
o   General site clean-up
o   Landscape restorations.
·         Depot Street (North of Prairie Street), Phase II
o   Asphalt patching behind new curb & gutter
o   Open parking stalls to commuter and resident parking – Tuesday, June 28th

Work along Kiess Drive is nearing completion with the exception of landscape restoration, general site clean-up, and other miscellaneous restorations. Thank you to all the residents during this extended construction time period due to several unforeseen delays throughout the process. Now that the roadway is paved, hopefully you are happy with the improvements to your street and neighborhood.

The work along Depot Street continues to move along as scheduled. It is anticipated that Phase II of the project will be completed near the beginning of next week and all parking stalls will be re-opened prior to the July 4th Holiday.

Following the July 4th Holiday, the paving phase will begin and take approximately 2-3 days. During this phase, commuter parking stalls will be open.  However, commuters will be ask to park in all available spots/parking lots outside the construction zone.   

Thanks again to everyone for their patience and understanding with the roadway improvements throughout the Village, especially to those residents with work completed along their street or within their neighborhoods.

Friday, June 17, 2016

Work On-Going along Kiess Drive and Depot Street

Work Completed Last week, June 13th to June 17th   
·         Kiess Drive
o   Poured concrete curb & gutter, driveways, and sidewalks
·         Depot Street (South of Prairie Street), Phase I
o   Closed commuter and residential parking stalls within work area
o   Performed storm sewer improvements as required
o   Removed and replaced concrete curb & gutter within work area

Work anticipated to be completed Next week, June 20th to June 24th  
·         Kiess Drive
o   Mill existing pavement surface layer
o   Perform patching of existing asphalt pavement as needed
o   Install new asphalt pavement surface layer
·         Depot Street (South of Prairie Street), Phase I
o   Perform asphalt patching around new concrete curb & gutter
o   Open parking stalls for commuter and resident parking, anticipated to be open by the end of the day on Monday, June 20th
·         Depot Street (North of Prairie Street), Phase II
o   Tuesday, June 21st - Close commuter parking stalls within work area
o   Saw-cut existing pavement and curb & gutter
o   Remove existing concrete curb & gutter
o   Pour concrete curb & gutter
o   Tuesday (6/28/16):
§  Asphalt patching behind new curb & gutter
§  Open parking stall previously closed during construction. 

The work on the south end of Depot Street went as planned last week and the parking stalls in this area are scheduled to be opened by Tuesday, June 21. Work on Phase II of the improvements, north of Prairie Street, is anticipated to begin on Tuesday, June 21st and completed by Tuesday, June 28th.  If everything goes as planned, the concrete curb & gutter replacement will be completed prior to the July 4th Holiday. Following the July 4th Holiday, the existing asphalt pavement will be removed and a new asphalt pavement will be installed.

Thank you again for all your patience and understanding as a significant amount of parking stalls are blocked off during the previous and upcoming weeks.

Friday, June 10, 2016

Kiess Drive Concrete to be Completed. Work along Depot Street Begins

Work Completed Last week, June 6th to June 10th  
·         Asphalt pavement paving along:
o   Norwood Terrace
o   Harrison Street
o   Covert Road
o   Castle Drive
o   Knollwood Lane
·         Kiess Drive (North Side of the Street):
o   Concrete curb & gutter, sidewalk, and driveway removals
o   Provided temporary access to driveways due to weather delays in pouring concrete.

Work anticipated to be completed Next week, June 13th to June 17th
·         Kiess Drive
o   Pour concrete curb & gutter, driveways, and sidewalks
o   Provide access to driveways once concrete has cured.
·         Depot Street (South of Prairie Street)
o   Close commuter and residential parking stalls within work area
o   Saw-cut existing pavement and curb & gutter
o   Remove existing concrete curb & gutter
o   Perform storm sewer repairs as required
o   Pour concrete curb & gutter
o   Monday (6/20/16):
§  Asphalt patching behind new curb & gutter
§  Open parking stall previously closed during construction.

Once the Depot Street south of Prairie Street is completed, the same process will continue on the north end of Depot Street between Prairie Street and Grove Street. This work is anticipated to begin on Tuesday, June 21st and be completed prior to the July 4th Holiday.

Friday, June 3, 2016

Asphalt Paving Continues

Work Completed Last week, May 30th to June 3rd
·         Asphalt pavement removal along:
o   Castle Drive
o   Knollwood Lane
o   Norwood Terrace
o   Harrison Street
o   Intersection of Shermer Road and Central Road
o   Harrison Street (Minor Patching)
o   Covert Road (Minor Patching)
·         Asphalt paving and/or patching along:
o   Intersection of Shermer Road and Central Road
o   Harrison Street (Minor Patching)
o   Norwood Terrace
o   Harrison Street
o   Covert Road (Minor Patching)

Work anticipated to be completed Next week, June 6th to June 10th
·         Asphalt paving (final surface) the remainder of areas not completed last week including:
o   Norwood Terrace
o   Harrison Street
o   Covert Road
o   Castle Drive
o   Knollwood Lane
·         Concrete Curb & Gutter Removal and Replacement
o   Kiess Drive