Friday, May 27, 2016

Pavement Resurfacing to Continue

Work Completed Last week, May 23rd to May 27th
·         Underground utility improvements consisting of storm sewer installation or repair
o   Near intersection of Central Road and Shermer Road
o   Kiess Drive
o   Norwood Terrace
o   Harrison Street
o   Imperial Drive
o   Executive Lane
o   Longmeadow Drive
·         Asphalt driveway replacement / repair (if impacted due to construction operations)
o   Kiess Drive
o   Harrison Street
o   Covert Road
o   Imperial Drive
o   Executive Lane
o   Longmeadow Drive
·         Complete concrete replacement along:
o   Near intersection of Central Road and Shermer Road
o   Kiess Drive
o   Norwood Terrace
o   Imperial Drive
o   Executive Lane
o   Longmeadow Drive

Work anticipated to be completed Next week, May 30th to June 3rd
·         Asphalt pavement removal and replacement along:
o   Castle Drive (south of Springdale Avenue)
o   Knollwood Lane ( west of Pfingsten Road)
o   Norwood Terrace
o   Harrison Street
o   MARS patches at Harrison Street, Covert Road, and Primrose Lane

Thank you to all the residents along the project sites that have had periodic work along their streets or experienced extended time out of their driveways due to unforeseen circumstances or project scheduling. Now that the majority of the storm sewer improvements are completed, the concrete that was previously removed is anticipated to be replaced by the end of the week.

In several areas, the now that the concrete and storm sewer improvements are completed, the roadway resurfacing can begin. In a few areas, additional concrete replacement needs to be performed on the opposite side of the street. For these residents, the remaining concrete work is scheduled to be completed within the next few weeks prior to the roadway resurfacing beginning.

No work will be performed on-site over the holiday weekend.

Have a fun and safe Memorial Day!!!

Monday, May 23, 2016

Storm Sewer and Driveway Replacements This Week

Work Completed Last week, May 16th to 20th  
·         Concrete Removal and Replacement
o   Harrison Street
o   Covert Road
o   Norwood Terrace
o   Kiess Drive (South Side)
o   Central Road, near Shermer Road
o   Imperial Drive
o   Executive Lane
o   Longmeadow Drive 

Work anticipated to be completed Next week, May 23rd to May 27th
·         Underground Improvements consisting of storm sewer installation or repair
o   Near intersection of Central Road and Shermer Road (storm sewer installation)
o   Kiess Drive
o   Norwood
o   Harrison
o   Imperial/Executive/Longmeadow
 
·         Asphalt Driveway Replacement/Repair (if impacted)
o   Kiess
o   Harrison
o   Covert
o   Imperial Drive
o   Executive Lane
o   Longmeadow Drive

Thank you to all the residents who are affected by the concrete curb & gutter removal and replacement.

Monday, May 16, 2016

Additional Work Week of May 16th

Additional Concrete Removal and Replacement to be performed along:
  • Imperial Drive
  • Executive Lane
  • Longmeadow Drive

Thanks again for all your patience and understanding.

Friday, May 13, 2016

Concrete Curb & Gutter Replacement to Begin

Work Completed Last Week, May 9th to 13th
·         Pavement Removal and Paving:
o   Central Road
o   Woodland Drive
o   Queens Lane
o   Pleasant Lane
o   Independence Avenue
o   Primrose Lane

Work Anticipated to be completed Next week, May 16th to 20th  
·         Concrete Removal and Replacement
o   Harrison Street
o   Covert Road
o   Norwood Terrace
o   Kiess Drive
o   Central Road, near Shermer Road 

Thank you to all the residents who are affected by the concrete curb & gutter removal and replacement. We understand the inconvenience it is not having access to your driveway for an extended period of time. Please understand we will do everything possible to minimize the inconvenience to the greatest extent possible.