Friday, July 15, 2016

Roadway Resurfacing Scheduled to be Completed Next Week

Work Completed Last week, July 11th to July 15th
·         Depot Street
o   Removed existing asphalt surface
o   Installed new asphalt pavement
o   Opened parking stalls to commuters and residents.
·         Roadways with asphalt removal and resurfacing performed
o   Primrose Lane
o   Elmwood  Avenue
o   Queens Lane
o   Meadow Lane
o   Canterbury Lane
o   Sussex Lane
·         Roadways with asphalt removal performed
o   Executive Lane: Imperial Drive to Longmeadow Drive
o   Imperial Drive: Executive Lane to Executive Lane
o   Longmeadow Drive: Thornwood Avenue to Executive Lane
·         All sites
o   General Site Clean-Up
o   Landscape restoration with topsoil and seed or sod

Work anticipated to be completed Next week, July 11th to July 15th  
·         Roadways to have new asphalt surface paved:
o   Executive Lane: Imperial Drive to Longmeadow Drive
o   Imperial Drive: Executive Lane to Executive Lane
o   Longmeadow Drive: Thornwood Avenue to Executive Lane
·         Pavement marking at locations where existing pavement marking were removed
·         Miscellaneous structure adjustments along various streets

Thanks again for all your patience and understanding as you deal with parking restrictions and pavement replacement along your streets.