Tuesday, July 12, 2016

Depot Street Construction to be Completed. Remaining Roadway Resurfacing On-Going

Work Completed Last week, July 4th to July 8th  
·         All sites
o   General Site Clean-Up
o   Landscape restoration with topsoil and seed or sod
·         Storm sewer improvements along Meadow Lane
·         Storm sewer improvements along Kiess Drive

Work anticipated to be completed This week, July 11th to July 15th  
·         Depot Street
o   Removal of existing asphalt surface
o   Perform necessary repairs to ensure stable base materials
o   Grade existing base in preparation for asphalt pavement
o   Install new asphalt pavement
o   Open parking stalls to commuters and residents.
·         Streets to have existing asphalt surface removed and repaved:
o   Executive Lane: Imperial Drive to Longmeadow Drive
o   Imperial Drive: Executive Lane to Executive Lane
o   Longmeadow Drive: Thornwood Avenue to Executive Lane
o   Primrose Lane
o   Elmwood  Avenue
o   Queens Lane
o   Meadow Lane
o   Canterbury Lane
o   Sussex Lane
·         All sites
o   General Site Clean-Up
o   Landscape restoration with topsoil and seed or sod

Landscape restorations are anticipated to be completed along the roadways that were previously resurfaced. In areas with minimal restoration or areas where the concrete curb & gutter was replaced, the landscape restoration will be completed with topsoil and seed. In areas where underground utility improvements were made, the landscape restoration will be performed with topsoil and sod.

During the Depot Street pavement resurfacing, the parking stalls will be closed during construction. We request you utilize other parking stalls during this time period. Additional information will be provided regarding the exact day the work will be completed.

Thanks again for all your patience and understanding as you deal with parking restrictions and pavement replacement along your streets.