Storm Sewer and Driveway Replacements This Week

Work Completed Last week, May 16th to 20th  
·         Concrete Removal and Replacement
o   Harrison Street
o   Covert Road
o   Norwood Terrace
o   Kiess Drive (South Side)
o   Central Road, near Shermer Road
o   Imperial Drive
o   Executive Lane
o   Longmeadow Drive 

Work anticipated to be completed Next week, May 23rd to May 27th
·         Underground Improvements consisting of storm sewer installation or repair
o   Near intersection of Central Road and Shermer Road (storm sewer installation)
o   Kiess Drive
o   Norwood
o   Harrison
o   Imperial/Executive/Longmeadow
 
·         Asphalt Driveway Replacement/Repair (if impacted)
o   Kiess
o   Harrison
o   Covert
o   Imperial Drive
o   Executive Lane
o   Longmeadow Drive

Thank you to all the residents who are affected by the concrete curb & gutter removal and replacement.