Friday, May 13, 2016

Concrete Curb & Gutter Replacement to Begin

Work Completed Last Week, May 9th to 13th
·         Pavement Removal and Paving:
o   Central Road
o   Woodland Drive
o   Queens Lane
o   Pleasant Lane
o   Independence Avenue
o   Primrose Lane

Work Anticipated to be completed Next week, May 16th to 20th  
·         Concrete Removal and Replacement
o   Harrison Street
o   Covert Road
o   Norwood Terrace
o   Kiess Drive
o   Central Road, near Shermer Road 

Thank you to all the residents who are affected by the concrete curb & gutter removal and replacement. We understand the inconvenience it is not having access to your driveway for an extended period of time. Please understand we will do everything possible to minimize the inconvenience to the greatest extent possible.